Location:
Treforest
Value:
£6 million
Date:
2025
Duration:
40 Weeks
Works:

Reinforced Concrete Frame

Comments:

TVC have – or are in the process of constructing a 4 storey RC frame with a roof slab.

Foundation to 1st floor 5285mm high, to include Retaining walls, 115no precast columns, 4 cores, elevated slab.

1st to 2nd floor construction 3700mm high to include 103 precast columns 4 cores, elevated slab.

2nd to 3rd floor construction 3700mm high to include 103 precast columns 4 cores, elevated slab and upstands .

3rd to 4th floor construction 3600mm high to include 67 precast columns, 3 cores, elevated slab and upstands

4th to roof construction 3600mm high to include 65 precast columns, 3 cores, elevated slab, upstands and precast roof light beams.