Margam Biomass Energy Park

Main Contractor

Interserve

Works

RC Frame

Value

£2 Million

Duration

40 weeks

Date
Category
Completed Projects
Tags
Concrete Frames, Interserve
About This Project

As Project Manager for the Margam Biomass Energy Plant, I worked with TVC during their appointment to provide reinforced concrete structures for the lift shaft including stairs, wood chip building, walls to the tipping bay, suspended and intermediate slabs and various other structures.

 

TVC assisted us throughout the project providing a knowledgeable and professional service within a very tight timeframe. The TVC approach to Health & Safety, Quality, Production and Site Management mirrors the values set by Interserve allowing us as the Main Contractor and TVC to work as a team and achieve the project goals.

Richard Kerley
Project Manager